Automatic PE Powder Dip-Coating Line for Wire Racks, 3,500 pcs/shift – Thanglong Metal Wares Joint Stock Company


KIEUAN designed, fabricated, installed and commissioned an automatic PE powder dip-coating line for Thanglong Metal Wares Joint Stock Company (Công ty CP Kim khí Thăng Long) in Sai Dong, Long Bien, Hanoi. The line coats steel wire racks at a design capacity of 3,500 pieces per shift. Installation was completed on 4 February 2024, and the line was fine-tuned and finalised through June 2024.

Project information

Client Thanglong Metal Wares Joint Stock Company
Location Sai Dong, Long Bien, Hanoi, Vietnam
Product PE-coated steel wire racks
KIEUAN scope Survey, design, fabrication, installation, commissioning, technology transfer
Design capacity 3,500 pieces per shift
Timeline October 2023 – June 2024

Requirements and design approach

Thanglong Metal Wares wanted to automate wire-rack coating within the footprint of an old paint line, reusing part of its equipment. After a site survey in October 2023, KIEUAN proposed:

  • A 66 m continuous overhead conveyor with 21 hangers at 3.15 m pitch (100 kg each), running on a run / stop cycle adjustable from 1 s to 10 min at 1 – 5 m/min.
  • A 2,000-litre fluidised powder bath on a 3-tonne automatic lift that rises around the parts for the time set on the PLC.
  • Two electrically heated ovens: a 12.85 m pre-heating oven (200 – 400°C) and a 9.5 m post-curing oven (180 – 220°C), with automatic doors and SCR power control.

Layout of the automatic dip-coating line
Line layout: 21 hangers, 66 m conveyor, 31.4 m system length

Fabrication and installation

All mechanical systems, ovens and control panels were built at KIEUAN's own factory in January 2024, then pre-assembled and test-run before leaving the fabrication shop. The equipment was dismantled, shipped and fully installed at Thanglong Metal Wares' factory on 4 February 2024.

Conveyor and ovens pre-assembled at KIEUAN workshop
Conveyor and ovens pre-assembled at the KIEUAN workshop

Fluidised powder bath with automatic lift
2,000-litre fluidised bath and 3-tonne lifting frame

PLC + HMI control cabinet of the dip-coating line
Central PLC + HMI control cabinet

Dipping area and fume extraction at Thanglong Metal Wares
Installed at Thanglong Metal Wares, completed 4 February 2024

Full-line trial run

From November 2023 to March 2024, KIEUAN dip-tested several powders and heat settings on samples supplied by Thanglong Metal Wares. The process runs: loading → pre-heating → fluidised-bed dipping → post-curing → cooling → unloading. In the test of 9 March 2024, the coating reached 350 – 400 µm thickness and 50 – 60 gloss with an even surface.

PE powder fluidising in the bath
Powder fluidising evenly in the dipping bath

PE-coated steel wire racks
Wire racks after PE coating, 350 – 400 µm

Dip-coated test samples with labelled settings
Test samples with settings written on the labels

Handover and production

After fine-tuning through June 2024, KIEUAN trained Thanglong Metal Wares' team and transferred the process so they can run the line and produce parts to specification.

Results

  • Design capacity of 3,500 pieces per shift, continuous and automatic.
  • Even PE coating, 350 – 400 µm thick, gloss 50 – 60.
  • Conveyor chain, guide rails and wall panels from the old line reused, lowering investment cost.

Talk to us about your coating line