Powder Coating + Liquid Painting Line for KOFFMANN Steel Door Factory
KIEUAN has completed an electrostatic powder coating and liquid painting line for the KOFFMANN Vietnam steel door factory in Industrial Park No. 5, Hung Yen. The project ran in 2 phases from April 2025 to May 2026, delivered turnkey: design, in-house manufacturing, installation, commissioning and operator training.
Project overview
Client
KOFFMANN Joint Stock Company
Location
Industrial Park No. 5, Xuan Truc, Hung Yen, Vietnam
Type
Steel door and 5D wood-grain steel door factory
KIEUAN scope
Powder coating + liquid painting line, curing ovens, overhead rail and lane-transfer system
Timeline
Phase 1: Apr–May 2025 · Phase 2: Dec 2025 – May 2026
Workshop before installation (Apr 2025)
Phase 1 – Ground-floor powder line (2025)
Powder booth with 2-stage Cyclone + Filter recovery, curing oven, overhead rail and control cabinets; accepted before operation on 30 May 2025.
Erecting the insulated-panel curing oven
Powder recovery cyclone
Phase 2 – Second-floor expansion for 5D doors (2025–2026)
9 m automatic powder coating booth with 2-stage Cyclone + Filter recovery
2 water-curtain liquid spray booths with inverter-controlled exhaust fans
3 electric curing ovens up to 220°C, 100 mm glass-wool panels
2 lane-transfer frames 32 m long, 60 hanger bars (100 kg each)
Oven rails with pneumatic locking pins
Installing the 2nd-floor lane-transfer frame and rails